April 11, 1956 (22nd Parliament, 3rd Session)

PC

Mr. Trainor

Progressive Conservative

1. What share of the cost of existing bridges over the Red and Assiniboine rivers in the greater *Winnipeg area between Headingley and Selkirk, was borne by the federal government?
2. When were these bridges built?
Answer by: Mr. Winters:
1 and 2. St. Andrews lock and dam bridge at Lockport, Man., was built between 19081914, at a cost of $550,184.87. Total cost borne by the federal government. Selkirk bridge was built between 1935-38, at a cost of $283,008.07. Total cost borne by the federal government.

Topic:   STARRED QUESTIONS
Subtopic:   BRIDGES, GREATER WINNIPEG-FEDERAL CONTRIBUTION